Sewerage Connection Permit

REQUIRED DOCUMENTS

A. Identity & Ownership

  • Aadhaar Card (Owner)
  • Property Tax Receipt (latest)
  • Ownership Proof:
    • Sale Deed / Title Deed
    • Possession Certificate
  • Building Number Certificate (from Municipality)

B. Building & Technical Documents

  • Approved Building Plan
  • Completion Certificate (if building completed)
  • Location Sketch / Site Plan
  • Plumbing Layout Plan (sewer line connection)

C. NOCs (if required)

  • Road Cutting Permission (if pipeline crosses road)
  • Consent from neighboring property (rare cases)
  • Environmental clearance (for commercial/large buildings)

D. Utility & Supporting Documents

  • Previous Water Connection Details (if any)
  • Septic Tank Details (if converting to sewer line)
  • Applicant Photograph
  • Mobile Number & Email ID

2. APPLICATION FORM FORMAT 

SEWERAGE CONNECTION APPLICATION FORM

To:
The Secretary
Thiruvananthapuram Municipal Corporation

Applicant Details:

  • Name:
  • Address:
  • Mobile Number:
  • Email ID:

Property Details:

  • Ward Number:
  • Door/Building Number:
  • Survey Number:
  • Property Tax Number:

Connection Details:

  • Type of Building: Residential / Commercial
  • Number of Floors:
  • Water Source: KWA / Well / Borewell
  • Existing Septic Tank: Yes / No

Technical Details:

  • Distance to Main Sewer Line:
  • Proposed Pipe Size:
  • Plumbing Contractor Name & License No:

Declaration:
I hereby declare that the above information is true and agree to follow all municipal sewerage rules.

Place:
Date:
Signature of Applicant


3. STEP-BY-STEP APPLICATION PROCESS

METHOD 1: ONLINE (Kerala – Sanchaya / e-Governance Portal)

Step 1: Visit Portal

  • Go to Municipal service portal (e.g., Sanchaya / Local Self Government portal)

Step 2: Login / Register

  • Create account using:
    • Mobile number
    • OTP verification

Step 3: Select Service

  • Choose:
    “Sewerage Connection / Drainage Connection”

Step 4: Fill Application

Enter:

  • Applicant details
  • Property details
  • Technical details

Step 5: Upload Documents

Upload scanned copies:

  • Aadhaar
  • Tax receipt
  • Building plan
  • Plumbing layout

Step 6: Pay Fees

  • Application fee
  • Connection charges
  • Road cutting charges (if applicable)

Step 7: Submit Application

  • Note Application Number for tracking

Step 8: Inspection

  • Municipal engineer/site inspector visits property

Step 9: Approval

  • After verification, approval is granted

Step 10: Connection Work

  • Authorized team connects property to sewer line

METHOD 2: OFFLINE (Municipal Office)

Step 1: Visit Office

Go to:

  • Engineering Section / Public Health Section

Step 2: Collect Form

  • Ask for:
    Sewerage Connection Application Form

Step 3: Fill Form

  • Complete all required details

Step 4: Attach Documents

  • Submit all required documents (self-attested)

Step 5: Pay Fees

  • Pay at municipal counter
  • Collect receipt

Step 6: Submit Application

  • Get acknowledgment receipt

Step 7: Site Inspection

  • Engineer inspects location

Step 8: Approval & Work Order

  • Permission issued
  • Connection scheduled

Step 9: Installation

  • Sewer line connected to main drainage system

4. FEES (APPROXIMATE)

Type Amount
Application Fee ₹100 – ₹500
Connection Fee ₹1,000 – ₹10,000
Road Cutting Based on area
Security Deposit ₹1,000 – ₹5,000

5. PROCESS TIME

  • Application Review: 3–7 days
  • Inspection: 3–5 days
  • Approval: 7–15 days total

6. IMPORTANT RULES

  • Do NOT connect illegally to sewer line
  • Septic tank must be properly closed (if converting)
  • Follow municipal pipe size standards
  • Only licensed plumbers allowed
  • Penalty for violations may apply

7. COMMON REASONS FOR REJECTION

  • Incomplete documents
  • Unauthorized building
  • No nearby sewer line
  • Incorrect technical details